Danh Mục Hồ Sơ Quản Lý Dự Án

 

Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title Ref. Document Title
1 Communication Document 2 Authorities 3 Sales Requirement Document 4.1 Consultant Document Design 4.2 Consultant Document Quantity Surveyor 4.3 Consultant Document Construction Management 5 Design Document 6.1 Package XX Contractor Document – Tender Stage – 6.2 Package XX Contractor Document – Contract Stage – 6.3 Package XX Contractor Document – Construction Stage – 7.XX Package XX Construction Document 8.XX Package XX Handover Document 9 Warranty Term Document
1.1 Project Directory 2.1 Letter/ Document 3.1 Construction Budget 4.1.1 Tender Document 4.2.1 Tender Document 4.3.1 Tender Document 5.1 Owner’s Requirement (Specification) 6.1.1 Pre-Qualification 6.2.1 Agreement/Contract 6.3.1 Budget 7.1 Schedule 8.1 Aceptance certificate for Completion Project 9.1 After Service Meeting
1.2 Organization Chart 2.2 Authorities procedure 3.1.1 Design 4.1.2 Consultant Contract 4.2.2 Consultant Contract 4.3.2 Consultant Contract 5.2 Standard 6.1.2 Call tender 6.2.3 Amendment of Contract/ Appendix 6.3.1.1 Contract Cost Summary Report 7.2 Monitoring and Control Documents Acceptance 9.2 After Service Inspection
1.3 Responsibility Matrix 2.3 Master plan approval 3.1.2 Construction 4.1.3 Consultant Budget Control 4.2.3 Consultant Budget Control 4.3.3 Consultant Budget Control 5.3 Master Plan 6.1.3 Letter of Interest 6.2.4 Extension of Time 6.3.2 Variation Order 7.3 Request for Approval Request for inspection and acceptance
1.4 Communication Procedure 2.4 Basic Design appraisal 3.1.3 Consultant 4.1.3.1 Payment 4.2.3.1 Payment 4.3.3.1 Payment 5.4 Infrastructure 6.1.4 Tender Document 6.2.5 Performance Bond Summary of Variation Order 7.3.1 Method Statement Checking and acceptance of completed project
1.4.1 Approval of QA/QC activity 2.5 Technical/detail drawing appraisal 3.1.4 Contingency 4.1.3.2 Variation Order 4.2.3.2 Variation Order 4.3.3.2 Variation Order 5.5 Site Survey Report 4.1.4.1 Tender Document 6.2.6 Insurance Variation Order History Log 7.3.2 Shop Drawing Internal minutes of checking and acceptance of completed project
1.4.2 Approval of Material 2.6 PCCC approval 3.2 Brochure 4.1.4 Documentation 4.2.4 Documentation 4.3.4 Documentation 5.6 Concept Design 4.1.4.2 Pre-Tender Estimate 6.3.3 Payment 7.3.3 Material Appendix
1.4.3 Approval of Variation Order 2.7 Power Connection approval 3.2.1 Unit (layout Plan) 4.1.4.1 Report 4.2.4.1 Report 4.3.4.1 Report 5.7 Basic Design 4.1.4.3 Tender drawing & Specification 6.3.3.1 Financial Report 7.4 Site Directions/Instructions List of approved amendment of drawing
1.4.4 Approval of Payment 2.8 Construction Permit 3.2.2 Common 4.1.4.2 Letter 4.2.4.2 Letter 4.3.4.2 Letter 5.8 Detail Design 6.1.5 Clarification of Bidding Document 6.3.3.2 Interim Payment Claim Item List of As-built drawing
1.4.5 Request for Information 3.3 Area information 4.1.5 Operations and Management 4.2.5 Operations and Management 4.3.5 Operations and Management 5.9 Design Schedule 6.1.5.1 Question IPC Summary Sheet List of Acceptance Minutes
1.4.6 Request for Inspection 3.3.1 Method of Area Calculation 4.1.5.1 Schedule 4.2.5.1 Schedule 4.3.5.1 Schedule 5.10 Construction Drawing 6.1.5.2 Answer Supporting Document 7.5 Non-Conformity Work List of Acceptance material
1.4.7 Request for Handover 3.3.2 Area Information 4.1.5.2 Meeting 4.2.5.2 Meeting 4.3.5.2 Meeting 5.11 Revised Design Drawing 6.1.6 Tender Submission 6.3.3.5 Final Payment List 8.2 As-Built Drawing
1.4.8 Site Instruction 3.4 Mock-Up room 4.1.6 Quality Control 4.2.6 Quality Control 4.3.6 Quality Control 5.11.1 Proposed Change Order 6.1.7 Bid Bond Closing 8.3 Warranty
1.4.9 Emergency communication 3.5 Scale Model 5.11.2 List of revised design drawing 6.1.8 Evaluation/Report Final Payment include follow Doc: 7.6 Meeting 8.4 Organization during warranty term
1.5 Assignment (each party) 3.6 Sales Gallery 5.11.3 Approved Amendment of Drawing 6.1.9 Negotiation, Interview Letter of Application for Final Payment Project Management Meeting 8.5 Operation and Maintenance Manual
Includes: 3.7 Hoarding 5.12 Landscape Design 6.1.10 Value Engineering Cost Reduction Application for Final Payment sheet Construction Management Meeting 8.6 Key List
Assignment letter 3.8 Project Name 5.13 ID design 6.1.11 Letter of Regret Summary of Final Account 7.7 Safety 8.7 Spare List
Diplomas 3.9 Event 5.14 Question and Answer 6.1.12 Letter of Acceptance Variation Order Site Patrol Report 8.8 Defect List
Professional Practise License 3.10 Schedule for handover to customer 5.15 Maintenance Book Quantities sheet of Final Account Safety Violation Notice 8.9 Authority Permission
CV 5.16 Fitting-Out guide line Evidences of the amount of item No2 Incident Report Fire Police
1.6 Guideline for Coding Copy of Interim Payment Certificate 7.8 Photo Water Supply
1.7 Holiday Leave Schedule Copy of Variation Order Approval Form Fixed View Sewage Water
Contract Extension Agreement Monthly Storm Water
Acceptance & Handover Minutes Daily Electric Supply
Transmittal form of Handing over the as-built document 7.9 Report of Lighting
Award Documents & Contracts Completion Transportation Connection
Site Instructions & Variation Orders Monthly Environment
Variation Orders Weekly DOC or MOC requirement
Claims Site Diary 8.10 Project Lessons Learned
Interim Progress Claims 7.10 Site Observation/ Site walk 8.11 HO Document Tracking
Final Accounts List
Completion, Handover & DLP Closing
Defects List 7.11 Inspection Document
As-built Drawings 7.12 Request for Information
Test Certificate 7.13 Test and Commission
Warranties 7.14 Project Earned Value Analysis
Operating Manuals 7.15 Letter
7.16 Handover Minutes
7.17 Acceptance Minutes
7.18 Transmittal

Leave a Reply

Your email address will not be published. Required fields are marked *

Translate »

You cannot copy content of this page

error: